Full design & build of 5 starter industrial units and associated circulation and hard standing areas.

All units incorporated disabled toilet facilities, three phase electric supply, aluminium glazed entrance screen and personnel door, tea point and dado block work to full building perimeter. Externally, all areas were fully kerbed and completed in SMA tarmacadam surfacing with flagged paving and full soft landscaping to satisfy the local planning authority. To accommodate the low lying level of the site all foul sewage was pumped to public sewer via a proprietary package pump station.

Project value £410,000.
Phase Two of this development is now underway comprising 5 office buildings and 4 warehouse units.